Question

1 Approved Answer

bConsider a manufacturing process depicted by the following flowchart. flowchart Station A has 3 parallel operators, A 1 , A 2 , and A 3

bConsider a manufacturing process depicted by the following flowchart.
flowchart
Station A has 3 parallel operators, A1, A2, and A3. Station C has 2 parallel operators, C1 and C2. Each unit only needs to be processed by one of the operators A1, A2 and A3. After being processed at Station B (with a single operator), a unit then needs to be processed by either C1 or C2. The process time of the individual operators are given as follows.
A1, A2, and A3: 21 minutes
B: 14 minutes
C1 and C2: 2 minutes.
The process initiates the production of a new unit every 28 minutes. What is the labor productivity (in units/hour) of this process?
Note: 1. Round your final answer to 2 decimal places if it is not a whole number.
2. Operators are paid even if they are idle.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Sustainability and Supply Chain Management

Authors: Jay Heizer, Barry Render, Paul Griffin

2nd Canadian edition

978-0133764345

More Books

Students also viewed these General Management questions

Question

Identify the elements in an organizations internal environment

Answered: 1 week ago