Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,730,000. The project was begun in 2015 and
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,730,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below: 2016 $1,030,000 2015 Costs incurred during the year 476,000 Estimated costs to complete Billings during the year Cash collections during the year 884,000 470,000 1,315,000 370,000 1,415,000 C)
Step by Step Solution
There are 3 Steps involved in it
Step: 1