Question
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,900,000. The project was begun in 2015 and
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,900,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below: |
2015 | 2016 | |||||||||
Costs incurred during the year | $ 420,000 | $1,200,000 | ||||||||
Estimated costs to complete | 980,000 | 0 | ||||||||
Billings during the year | 450,000 | 1,450,000 | ||||||||
Cash collections during the year | 350,000 | 1,550,000 | ||||||||
|