Question

1 Approved Answer

Beavis Construction Company was the low bidder on a construction project to build an office building for $8,000,000. The project was begun in 2017 and

Beavis Construction Company was the low bidder on a construction project to build an office building for $8,000,000. The project was begun in 2017 and completed in 2019. Cost and other data are presented below:

2017 2018 2019

Costs incurred during the year $ 1,500,000 $4,500,000 $1,550,000

Estimated costs to complete 4,500,000 1,500,000 -0-

Billings during the year 1,400,000 5,200,000 1,400,000

Cash collections during the year 1,000,000 4,000,000 3,000,000

Assume that Beavis recognizes revenue on this contract over time according to percentage of completion. Also assume that all construction costs are paid in Cash.

Required:

Compute the amount of revenue and gross profit recognized during 2017 and 2018.

Extra credit (9 points):

Prepare the 2018 journal entries to record:

a. Construction costs incurred during the year

b. Billings

c. Cash Collections

d. Revenue Recognition

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Sound Investing, Chapter 5 - Cost Allocation

Authors: Kate Mooney

8th Edition

007171927X, 9780071719278

More Books

Students also viewed these Accounting questions

Question

Understand how HRM can support a sustainable competitive advantage.

Answered: 1 week ago

Question

Develop knowledge of the Italian entrepreneurial business context.

Answered: 1 week ago