Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,890,000. The project was begun in 2017 and
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,890,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below:
2017 | 2018 | |||||
Costs incurred during the year | $ | 423,000 | $ | 1,190,000 | ||
Estimated costs to complete | 987,000 | 0 | ||||
Billings during the year | 445,000 | 1,445,000 | ||||
Cash collections during the year | 345,000 | 1,545,000 | ||||
Assume that Beavis recognizes revenue on this contract over time according to percentage of completion. Required: Compute the amount of gross profit recognized during 2017 and 2018.
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,890,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below:
2017 | 2018 | |||||
Costs incurred during the year | $ | 423,000 | $ | 1,190,000 | ||
Estimated costs to complete | 987,000 | 0 | ||||
Billings during the year | 445,000 | 1,445,000 | ||||
Cash collections during the year | 345,000 | 1,545,000 | ||||
Assume that Beavis recognizes revenue on this contract over time according to percentage of completion. Required: Compute the amount of gross profit recognized during 2017 and 2018.
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started