Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2012 and

Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2012 and completed in 2013. Cost and other data are presented below:

2012 2013
Costs incurred during the year $ 450,000 $1,100,000
Estimated costs to complete 1,050,000 0
Billings during the year 400,000 1,400,000
Cash collections during the year 300,000 1,500,000

Assume that Beavis recognizes revenue on this contract over time according to percentage of completion.

Required:
Perpare all journal entries related to the construction project in 2012 and 2013

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Principles Of Auditing And Other Assurance Services

Authors: Ray Whittington, Kurt Pany

17th Edition

0073379654, 9780073379654

More Books

Students also viewed these Accounting questions