Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,700,000. The project was begun in 2020 and

Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,700,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below:

2020 2021
Costs incurred during the year $ 486,500 $ 1,000,000
Estimated costs to complete 903,500 0
Billings during the year 455,000 1,245,000
Cash collections during the year 355,000 1,345,000

Assume that Beavis recognizes revenue on this contract over time according to percentage of completion. Required: Compute the amount of gross profit recognized during 2020 and 2021.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Anxiety Audit

Authors: Lynn Lyons

1st Edition

0757324258, 978-0757324253

More Books

Students also viewed these Accounting questions

Question

What is the formula to calculate the mth Fibonacci number?

Answered: 1 week ago

Question

How can you develop media literacy?

Answered: 1 week ago