Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,890,000. The project was begun in 2015 and
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,890,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below: |
2015 | 2016 | ||
Costs incurred during the year | $ 423,000 | $1,190,000 | |
Estimated costs to complete | 987,000 | 0 | |
Billings during the year | 445,000 | 1,445,000 | |
Cash collections during the year | 345,000 | 1,545,000 | |
Required information
Assume that Beavis recognizes revenue on this contract over time according to percentage of completion. |
Required: |
Prepare all journal entries to record costs, billings, collections, and profit recognition. (If no entry is required for a transaction/event, select "No journal entry required" in the first account field.) |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started