Question
Before a firm establishes sourcing relationship with a supplier for repeated purchase, firms often pre-audit the supplier to ensure that the supplier is in healthy
Before a firm establishes sourcing relationship with a supplier for repeated purchase, firms often pre-audit the supplier to ensure that the supplier is in healthy financial status and has the capability to comply with the supply contracts. The audit process is very involved. The first phase of the audit involves obtaining "knowledge of the business." This phase of the audit requires the activities listed below.
Questions:
Draw the project network and implement the network model in the provided template to figure out the minimum number of days needed to complete the first phase of the audit.
Now that Assume that the first phase must be completed within 40 days. Modify the model in part a (in a separate workbook) to figure out the plan for project crashing.
Please show solver to complete this assignment
A BCDEFG Determine terms of engagement Appraisal of auditability risk and materiality Identification of types of transactions and possible errors Systems description Verification of, systems description Evaluation of internal controls Design of audit approach Preds. A ACDBF B, E Duration (days) 3 6 14 8 4 8 9
Step by Step Solution
3.34 Rating (157 Votes )
There are 3 Steps involved in it
Step: 1
Here is the project network for the first phase of the audit A B C D E F G 3 6 14 8 4 8 9 The following is the meaning of the networks nodes and arrow...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started