Before beginning this activity, review sections 8-2 and 8-2a in the textbook. An assembly line with 30 activities is to be balanced. The total amount
Before beginning this activity, review sections 8-2 and 8-2a in the textbook.
An assembly line with 30 activities is to be balanced. The total amount of time to complete all 30 activities is 60 minutes. The longest activity takes 2.4 minutes, and the shortest takes 0.3 minutes. The line will operate for 480 minutes per day.
-
- What are the maximum and minimum cycle times?
- How much daily output will be achieved by each of those cycle times? Tip: Use the formula provided in the text: Cycle Time (CT) = Available Time to Produce (A) / Demand Forecast (D) CT = A/R and apply the Cycle Time to the Available Minutes Per Day
Suppose, now, the line is balanced using 14 workstations and a finished product can be produced every 4.5 minutes.
-
- What is the production rate (daily output) in units per day?
- What is the assembly-line efficiency? Tip: Use the formula provided in the text: Sum of all tasks / Number of Workstations (N) * Cycle Time (CT)
- What would be the Idle Time in this scenario? Tip: Use the formula provided in the text
How do you feel about the level of efficiency and idle time determined? Is this realistic and sustainable? Explain your rationale.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started