Question
1 Approved Answer
begin{tabular}{cccc} hline Activity & Duration (weeks) & Precedes & Crash Cost/Week hline A (start) & 3 & B, C & $370 B &
\begin{tabular}{cccc} \hline Activity & Duration (weeks) & Precedes & Crash Cost/Week \\ \hline A (start) & 3 & B, C & $370 \\ B & 2 & E & $120 \\ C & 5 & F & $240 \\ E & 1 & F & $160 \\ F (end) & 3 & & $400 \\ \hline \end{tabular} activity down to 0 weeks duration