Bell computer is planning to launch a new high-end server. Nine steps or tasks are required to assemble this computer. Daily demand is expected to

Bell computer is planning to launch a new high-end server. Nine steps or tasks are required to assemble this computer. Daily demand is expected to be 81 units and there are three 8-hour shifts available each day to meet this production quota.

Task Req'd Time (in minutes) Predecessor
A 16 None
B 15 A
C 6 B
D 5 B
E 11 A
F 4 C, D
G 7 F
H 16 E
I 5 G, H

1, What is the takt time (in minutes) for this production line? (Round your answer to a one decimal place.)

2, What is the cycle time (in minutes) for this production line?

3, What is the combined idle time (in minutes) for this production line?

4, What is the overall efficiency for this production line? (answer as a percentage, and display your answer to two decimal places.) %

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Small Business Management Entrepreneurship and Beyond

Authors: Timothy s. Hatten

5th edition

538453141, 978-0538453141

More Books

Students also viewed these General Management questions

Question

What is the difference between pool boiling and flow boiling?

Answered: 1 week ago