Question
Below are a list of value-added and non-value-added quality control activities. Part 1: Analyze the percentage of value-added and non-value-added activities. Show your work. Part
Below are a list of value-added and non-value-added quality control activities.
Part 1: Analyze the percentage of value-added and non-value-added activities. Show your work. Part 2: After thoroughly reviewing all the activities, you realize you cannot eliminate any of the non-value-added activities. List three plans for reducing the monetary impact of the non-value-added activities. Please avoid bullets for this submission and be specific with your recommendations. For example, "Increase training" is not specific and will not receive full points.
Quality Control Activities | Activity Cost | Classification |
Design engineering | $ 75,000.00 | Value-added |
Disposing of rejected materials | $ 170,000.00 | Non-value-added |
Finished goods inspection | $ 125,000.00 | Value-added |
Materials inspection | $ 70,000.00 | Value-added |
Preventive maintenance | $ 125,000.00 | Value-added |
Processing returned materials | $ 135,000.00 | Non-value-added |
Disposing of scrap | $ 215,000.00 | Non-value-added |
Assessing vendor quality | $ 35,000.00 | Value-added |
Rework | $ 410,000.00 | Non-value-added |
Warranty work | $ 275,000.00 | Non-value-added |
Total activity cost | $ 1,635,000.00 |
Below are a list of value-added and non-value-added quality control activities.
Part 1: Analyze the percentage of value-added and non-value-added activities. Show your work. Part 2: After thoroughly reviewing all the activities, you realize you cannot eliminate any of the non-value-added activities. List three plans for reducing the monetary impact of the non-value-added activities. Please avoid bullets for this submission and be specific with your recommendations. For example, "Increase training" is not specific and will not receive full points.
Quality Control Activities | Activity Cost | Classification |
Design engineering | $ 75,000.00 | Value-added |
Disposing of rejected materials | $ 170,000.00 | Non-value-added |
Finished goods inspection | $ 125,000.00 | Value-added |
Materials inspection | $ 70,000.00 | Value-added |
Preventive maintenance | $ 125,000.00 | Value-added |
Processing returned materials | $ 135,000.00 | Non-value-added |
Disposing of scrap | $ 215,000.00 | Non-value-added |
Assessing vendor quality | $ 35,000.00 | Value-added |
Rework | $ 410,000.00 | Non-value-added |
Warranty work | $ 275,000.00 | Non-value-added |
Total activity cost | $ 1,635,000.00 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started