Below are a list of value-added and non-value-added quality control activities. Part 1: Analyze the percentage of value-added and non-value-added activities. Show your work. Part

Below are a list of value-added and non-value-added quality control activities.

Part 1: Analyze the percentage of value-added and non-value-added activities. Show your work. Part 2: After thoroughly reviewing all the activities, you realize you cannot eliminate any of the non-value-added activities. List three plans for reducing the monetary impact of the non-value-added activities. Please avoid bullets for this submission and be specific with your recommendations. For example, "Increase training" is not specific and will not receive full points.

Quality Control Activities Activity Cost Classification
Design engineering $ 75,000.00 Value-added
Disposing of rejected materials $ 170,000.00 Non-value-added
Finished goods inspection $ 125,000.00 Value-added
Materials inspection $ 70,000.00 Value-added
Preventive maintenance $ 125,000.00 Value-added
Processing returned materials $ 135,000.00 Non-value-added
Disposing of scrap $ 215,000.00 Non-value-added
Assessing vendor quality $ 35,000.00 Value-added
Rework $ 410,000.00 Non-value-added
Warranty work $ 275,000.00 Non-value-added
Total activity cost $ 1,635,000.00

Below are a list of value-added and non-value-added quality control activities.

Part 1: Analyze the percentage of value-added and non-value-added activities. Show your work. Part 2: After thoroughly reviewing all the activities, you realize you cannot eliminate any of the non-value-added activities. List three plans for reducing the monetary impact of the non-value-added activities. Please avoid bullets for this submission and be specific with your recommendations. For example, "Increase training" is not specific and will not receive full points.

Quality Control Activities Activity Cost Classification
Design engineering $ 75,000.00 Value-added
Disposing of rejected materials $ 170,000.00 Non-value-added
Finished goods inspection $ 125,000.00 Value-added
Materials inspection $ 70,000.00 Value-added
Preventive maintenance $ 125,000.00 Value-added
Processing returned materials $ 135,000.00 Non-value-added
Disposing of scrap $ 215,000.00 Non-value-added
Assessing vendor quality $ 35,000.00 Value-added
Rework $ 410,000.00 Non-value-added
Warranty work $ 275,000.00 Non-value-added
Total activity cost $ 1,635,000.00

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Keys To Reading An Annual Report

Authors: George T. Friedlob, Ralph E. Welton

4th Edition

0764139150, 978-0764139154

More Books

Students also viewed these Accounting questions