Below are the project steps for the creation of a TV advertisement for BoomBam, which is a new energy drink that the musician BoomBam has
Below are the project steps for the creation of a TV advertisement for BoomBam, which is a new energy drink that the musician BoomBam has created.
1. What is the latest time (in days) that Activity B can finish?
A. 8
B. 9
C. 12
D. 13
2. What is the latest time (in days) that Activity D can start?
A. 8
B. 9
C. 12
D. 13
3. How many paths are there in your network diagram of the above project?
A. 1
B. 2
C. 3
D. 4
\begin{tabular}{|c|c|c|c|} \hline Activity & \begin{tabular}{c} Duration \\ (days) \end{tabular} & Description & \begin{tabular}{c} Preceding \\ Activity(ies) \end{tabular} \\ \hline A & 5 & \begin{tabular}{c} Create script for \\ advertisement \end{tabular} & - \\ \hline B & 3 & Book technical crew & A \\ \hline C & 3 & Book actors & A \\ \hline D & 4 & \begin{tabular}{c} Create props and \\ costumes \end{tabular} & B,C \\ \hline E & 5 & Book location & C \\ \hline F & 6 & Filming and editing & D,E \\ \hline \end{tabular}Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started