Question

1 Approved Answer

Below is a project WBS with cost apportioned by percents. Router systems project Cost: $600,000 Definition 10% Design 40% Implementation 50% Objectives 4% Requirements 6%

image text in transcribed
image text in transcribed
Below is a project WBS with cost apportioned by percents. Router systems project Cost: $600,000 Definition 10% Design 40% Implementation 50% Objectives 4% Requirements 6% In-house testing 40% Customer testing & review 10% Inputs 3% Outputs 3% Files 4% Interfaces 10% Programming 20% The original cost, as shown in the WBS, was $600,000. However, recently, the cost estimate has increased to $650,000. Use this information to answer the problems that follow. (For some reason, D2L keeps dropping the figure. If it is missing, it is the figure from Exercise 5.3 in the textbook.) Question 7 (2 points) What is the revised cost for Design? Your Answer: Answer Question 8 (2 points) What is the revised cost for Requirements? Your Answer: Answer Question 9 (2 points) What is the revised cost for In-house testing? Your

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The 10 Step Formula To Teach Your Easy

Authors: Catherine E Storing

1st Edition

1735644706, 978-1735644707

More Books

Students also viewed these Finance questions

Question

staffered elections

Answered: 1 week ago

Question

2-1. What are six characteristics of effective teams? [LO-1]

Answered: 1 week ago

Question

2-5. What are the three main types of active listening? [LO-4]

Answered: 1 week ago