Below is Part A's product structure with lead times. 1. What is the minimum planning horizon for part A? 2. If the lead time
Below is Part A's product structure with lead times. 1. What is the minimum planning horizon for part A? 2. If the lead time for part G was reduced by 50%, what would the new minimum planning horizon be for part A? A LT=5 B LT=5 C D LT=3 LT=10 E LT=3 F LT=5 G LT=18 H LT=10 J LT=12 LT=12 K LT=5 L LT=5 M LT=12