Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Below is the cumulative percentage of work complete per task per week: Cumulative Percentage Complete 1 2 3 4 Task 1 40 62% 100% Task

  • Below is the cumulative percentage of work complete per task per week:

Cumulative Percentage Complete
1 2 3 4
Task 1 40 62% 100%
Task 2 25% 75% 100%
Task 3 5% 7% 25% 55%
Task 4 5%

What are the CEV, CPI, and CV at the end or week 4? What is the SPI?

FCAC (3 Methods)

  • Assume the project continues to completion with no changes to the CPI, what is the expected FCAC? Is this under or over budget?
  • Assume the project continues based on its original budgeted costs, what is the expected FCAC? Is this under or over budget?
  • Using the SPI, is this project is on schedule?
  • Bonus points (+5): Assume the project continues based on its original budgeted cost except that there is a $7,500 change order from the customer for a rapid electric car charger on a wall the kitchen shares with the garage. What are the new expected FCACs? Do you think it can still be finished in the 5-week time period? Why/why not?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Managerial Accounting

Authors: Peter C. Brewer

Custom Edition

0077842987, 978-0077842987

More Books

Students also viewed these Accounting questions