Below is the cumulative percentage of work complete per task per week: Cumulative Percentage Complete 1 2 3 4 Task 1 40 62% 100% Task
- Below is the cumulative percentage of work complete per task per week:
Cumulative Percentage Complete | ||||
1 | 2 | 3 | 4 | |
Task 1 | 40 | 62% | 100% | |
Task 2 | 25% | 75% | 100% | |
Task 3 | 5% | 7% | 25% | 55% |
Task 4 | 5% |
What are the CEV, CPI, and CV at the end or week 4? What is the SPI?
FCAC (3 Methods)
- Assume the project continues to completion with no changes to the CPI, what is the expected FCAC? Is this under or over budget?
- Assume the project continues based on its original budgeted costs, what is the expected FCAC? Is this under or over budget?
- Using the SPI, is this project is on schedule?
- Bonus points (+5): Assume the project continues based on its original budgeted cost except that there is a $7,500 change order from the customer for a rapid electric car charger on a wall the kitchen shares with the garage. What are the new expected FCACs? Do you think it can still be finished in the 5-week time period? Why/why not?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started