Question
Benitez Company currently outsources a relay switch that is a component in one of its products. The switches cost $20 each. The company is considering
Benitez Company currently outsources a relay switch that is a component in one of its products. The switches cost $20 each. The company is considering making the switches internally at the following projected annual production costs:
The company expects an annual need for 5,000 switches. If the company makes the product, it will have to utilize factory space currently being leased to another company for $1,500 a month. If the company decides to make the parts, total costs will be:
$10,500 more than if the switches are purchased.
$30,500 more than if the switches are purchased.
$27,000 less than if the switches are purchased.
$20,000 less than if the switches are purchased.
Unit-level material cost Unit-level labor cost Unit-level overhead Batch-level set-up cost (5,000 units per batch) Product-level supervisory salaries Allocated facility-level costs 3 $25,000 $37,500 $20,000Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started