Bernard Cabin Construction Company uses the percentage-of-completion method with the cost-to-cost method of measuring progress. Find the percentage completed and the amount of revenue in
Bernard Cabin Construction Company uses the percentage-of-completion method with the cost-to-cost method of measuring progress. Find the percentage completed and the amount of revenue in gross profit to be recognized for each year based on the following information.
Contract Price $710,000
2015 2016 2017
Actual Construction Cost
Incurred During the Year $187650 (11,150) $261,500
Estimated Total Costs $417,000 $350,000 $438,000
Begin by computing percentage of completion for each year (Round to nearest whole percent)
2015 2016 2017
Cumulative % complete? ? ? ?
Next compute the amount of revenue and gross profit to be recognized for each year. (Enter 0 for any zero amount. Enter percentage to nearest whole percent.
Revenue and Gross Profit Recognition 2015 2016 2017
Contract Price ? ? ?
Percent Complete %? %? %?
Cumulative Revenue ? ? ?
Revenue recognized in prior years ? ? ?
Current year revenue ? ? ?
Less actual costs ? ? ?
Gross profit recognized in the current year ? ? ?
Please answer all question marks
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started