Question
Best Tire manufactures tires for all-terrain vehicles. Best uses job costing and has a perpetual inventory system. On November 22, Best received an order for
Best
Tire manufactures tires for all-terrain vehicles.
Best
uses job costing and has a perpetual inventory system. On
November
22,
Best
received an order for
130
TX tires from ATV Corporation at a price of
$80
each. The job, assigned number 298, was promised for
December
10. After purchasing the materials,
Best
began production on
November
30 and incurred the following direct labor and direct materials costs in completing the order:
LOADING...
(Click the icon to view the costs.)
Best
allocates manufacturing overhead to jobs on the basis of the relation between expected overhead costs
($540,000)
and expected direct labor hours
(20,000).
Job 298 was completed on
December
3 and shipped to ATV on
December
5.
Read the requirements
LOADING...
Requirement 1. Prepare a job cost record for Job 298.
Calculate the predetermined overhead rate, then apply manufacturing overhead to the job. Begin by identifying the formula and computing the predetermined overhead rate.
| Estimated yearly overhead costs |
| = | Predetermined overhead rate |
Part 2
| 540000 | 20000 | = | per hour |
Part 3
Complete the job cost record in order of direct materials, direct labor, and allocated manufacturing overhead. Then prepare the overall cost summary. (List the dates in chronological order. Enter the labor time records in the correct row according to date. If an input field is not used in the table, leave the input field empty; do not enter a zero.)
Job Cost Record | |||
Job No. | 298 |
| |
Customer Name | ATV Corporation | ||
Job Description | 130 TX tires | ||
Date Promised 12-10 |
| ||
| Direct Materials | ||
|
|
| |
| Requisition |
| |
Date | Number | Amount | |
20XX |
|
| |
1130 | 437 | 960 | |
122 | 439 | ||
|
|
| |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
Totals |
|
|
| |||
| |||
| |||
|
| ||
Date Started 11-30 | |||
Direct Labor | |||
Labor Time |
| ||
Record |
| ||
Number | Amount | ||
|
| ||
1896 | 216 | ||
|
| ||
|
| ||
|
| ||
|
| ||
|
| ||
|
| ||
|
|
| |||
Date Completed 12-3 |
| ||
Manufacturing Overhead Allocated | |||
|
|
| |
|
|
| |
Date | Rate | Amount | |
|
|
| |
123 | 22 | per |
|
| direct labor hr. | ||
Overall Cost Summary | |||
Direct Materials |
| ||
Direct Labor |
| ||
Manufacturing Overhead |
| ||
Allocated |
| ||
Total Job Cost |
|
|
Part 4
Requirement 2. Calculate the total profit and the per-unit profit for Job 298. (Round your answer to two decimal places.)
Job 298 | |
Sales |
|
Less: Cost of job |
|
Total profit on job |
|
Number of tires |
|
Per-unit profit |
|
Data table
Date | Labor Time Record No. | Description | Amount |
---|---|---|---|
11/30 | 1896 | 12 hours at $18 | $216 |
12/3 | 1904 | 30 hours at $14 | $420 |
Date | Materials Requisition No. | Description | Amount |
---|---|---|---|
11/30 | 437 | 60 lbs. rubber at $16 | $960 |
12/2 | 439 | 40 meters polyester fabric at $12 | $480 |
12/3 | 501 | 100 meters steel cord at $10 | $1,000 |
pop-up content ends
PrintDone
.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started