Big Sound Inc. manufactures two products: receivers and loudspeakers. The factory overhead incurred is as follows: 1 Indirect labor $400,400.00 2 Subassembly Department 198,800.00 3

Big Sound Inc. manufactures two products: receivers and loudspeakers. The factory overhead incurred is as follows:

1

Indirect labor

$400,400.00

2

Subassembly Department

198,800.00

3

Final Assembly Department

114,800.00

4

Total

$714,000.00

The activity base associated with the two production departments is direct labor hours. The indirect labor can be assigned to two different activities as follows:

1

Activity

Budgeted Activity Cost

Activity Base

2

Setup

$138,600.00

Number of setups

3

Quality control

261,800.00

Number of inspections

4

Total

$400,400.00

The activity-base usage quantities and units produced for the two products follow:

Number of Number of Direct Labor Hours Direct Labor Hours
Setups Inspections Subassembly Final Assembly Units Produced
Receivers 80 450 875 525 7,000
Loudspeakers 320 1,750 525 875 7,000
Total 400 2,200 1,400 1,400 14,000
Required:
1. Determine the factory overhead rates under the multiple production department rate method. Assume that indirect labor is associated with the production departments, so that the total factory overhead is $420,000 and $294,000 for the Subassembly and Final Assembly departments, respectively.* **
2. Determine the total and per-unit factory overhead costs allocated to each product, using the multiple production department overhead rates in (1).* **
Complete the Activity Tables for Receivers and Loudspeakers.
3. Determine the activity rates, assuming that the indirect labor is associated with activities rather than with the production departments.*
4. Determine the total and per-unit cost assigned to each product under activity-based costing.*
5. Explain the difference in the per-unit overhead allocated to each product under the multiple production department factory overhead rate and activity-based costing methods.
* If required, round your answers to two decimal places.
** Refer to the Amount Descriptions list provided for the exact wording of the answer choices for text entries.

Amount Descriptions

Direct materials

Final Assembly

Department

Loudspeakers

Quality Control

Receivers

Setup

Subassembly Department

. Determine the factory overhead rates under the multiple production department rate method. Assume that indirect labor is associated with the production departments, so that the total factory overhead is $420,000 and $294,000 for the Subassembly and Final Assembly departments, respectively. If required, round your answers to two decimal places. Refer to the Amount Descriptions list provided for the exact wording of the answer choices for text entries.

1

Department

Production Department Rate

2

per direct labor hour

3

per direct labor hour

2. Determine the total and per-unit factory overhead costs allocated to each product, using the multiple production department overhead rates in (1). If required, round your answers to two decimal places. Refer to the Amount Descriptions list provided for the exact wording of the answer choices for text entries.

1

Product

Total Factory Overhead

Factory Overhead Per Unit

2

3

Complete the Activity Tables for Receivers and Loudspeakers.
3. Determine the activity rates, assuming that the indirect labor is associated with activities rather than with the production departments.*
4. Determine the total and per-unit cost assigned to each product under activity-based costing.*
* If required, round your answers to two decimal places.
Receivers
Activity Activity- Activity Activity
Usage X Rate = Cost
Setup setups /setup
Quality Control insp. /insp.
Subassembly Department dlh /dlh
Final Assembly Department moves /move
Total
Number of units
Activity cost per unit

Complete the Activity Table for Loudspeakers.
3. Determine the activity rates, assuming that the indirect labor is associated with activities rather than with the production departments.*
4. Determine the total and per-unit cost assigned to each product under activity-based costing.*
* If required, round your answers to two decimal places.
Loudspeakers
Activity Activity- Activity Activity
Usage X Rate = Cost
Setup setups /setup
Quality control insp. /insp.
Subassembly Dept. dlh /dlh
Final Assembly Dept.
Total
Number of units
Activity cost per unit

5. Explain the difference in the per-unit overhead allocated to each product under the multiple production department factory overhead rate and activity-based costing methods. Check all that apply.

The activity-based overhead allocation reveals that receivers are more costly on a per-unit basis than are the loudspeakers.

The multiple production department factory overhead rate method distorts the unit costs.

Loudspeakers have fewer setups and inspection activities than do receivers, so receivers have higher activity costs per unit.

The activity-based method separately accounts for the setup and quality-control activity costs, decreasing cost distortion.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting Theory

Authors: William R Scott

5th Edition

0132072866, 978-0132072861

More Books

Students also viewed these Accounting questions