Bill Edstrom, managing partner at a biomedical consulting firm, has requested your expert advice in devising the best schedule for the following consulting projects, starting
Bill Edstrom, managing partner at a biomedical consulting firm, has requested your expert advice in devising the best schedule for the following consulting projects, starting at the beginning of the day on February
DESCRIPTION OF CONSULTATION
CALL RECEIVED
TASK LENGTH COMPANY DATE TIME DUE DATE CLOSE
OF BUSINESS
I days Novartis Corp. February AM February
II day Reardon Biotech Corp. February AM February
III days Vertex Pharmaceuticals February AM February
IV days OSI Pharmaceuticals February PM February
The consulting firm charges a flat rate of $ per day. All four firms impose fines for lateness. Reardon Biotech charges a $perday fine for each day that the completion of the consulting work is past the due date; Vertex Pharmaceuticals, Novartis, and OSI Pharmaceuticals all charge a fine of $ per day for each day late.
Prepare alternative schedules based on the following priority rules: SOT, FCFS EDD, STR and another rulelongest processing time LPT which orders jobs according to longest assigned first, second longest assigned second, and so on For the sake of simplicity, assume that consulting work is performed seven days a week.
a Calculate the total costs sum of the late fines for each rule.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started