Question

1 Approved Answer

Black Bear Construction Company has a contract to construct a $6,000,000 bridge at an estimated cost of $5,300,000. The contract is to start in July

Black Bear Construction Company has a contract to construct a $6,000,000 bridge at an estimated cost of $5,300,000. The contract is to start in July 2017, and the bridge is to be completed in October 2019. The following data pertain to the construction period.

Costs to date 2017: $1,325,000 2018: $3,780,000 2019: $5,430,000 Estimated costs to complete 2017:3,975,000 2018: $1,620,000 2019: $0

What is the percentage of contract completed by 2018?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting Tools for business decision making

Authors: Jerry J. Weygandt, Paul D. Kimmel, Donald E. Kieso

5th edition

470506954, 471345881, 978-0470506950, 9780471345886, 978-0470477144

More Books

Students also viewed these Accounting questions

Question

What factors in Nooyis Five C model facilitate employee trust?

Answered: 1 week ago