Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Blast it ! said David Wilson, president of Teledex Company. We ve just lost the bid on the Koopers job by $ 2 , 0

Blast it! said David Wilson, president of Teledex Company. Weve just lost the bid on the Koopers job by $2,000. It seems were either too high to get the job or too low to make any money on half the jobs we bid.
Teledex Company manufactures products to customers specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to jobs. The following estimates were made at the beginning of the year:
Department
Fabricating Machining Assembly Total Plant
Manufacturing overhead $350,000 $400,000 $90,000 $ 840,000
Direct labor $200,000 $ 100,000 $300,000 $600,000
Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturing costs in the three departments as follows:
Department
Fabricating Machining Assembly Total Plant
Direct materials $ 3,000 $200 $1,400 $4,600
Direct labor $ 2,800 $500 $6,200 $9,500
Manufacturing overhead ????
Required:
Using the companys plantwide approach:
Compute the plantwide predetermined rate for the current year.
Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job.
Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions:
Compute the predetermined overhead rate for each department for the current year.
Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job.
Explain the difference between the manufacturing overhead that would have been applied to the Koopers job using the plantwide approach in question 1(b) and using the departmental approach in question 2(b).
Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead). What was the companys bid price on the Koopers job using a plantwide predetermined overhead rate? What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cost And Management Accounting An Introduction

Authors: Colin Drury

5th Edition

1861529058, 978-1861529053

More Books

Students also viewed these Accounting questions

Question

Discuss global cultural differences in GLOBE dimensions.

Answered: 1 week ago

Question

LO1 Discuss the objectives of human resource management.

Answered: 1 week ago