Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Blast it! said David Wilson, president of Teledex Company. We've just lost the bid on the Koopers job by $2,000. It seems we're either too

image text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribed Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $2,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to jobs. The following estimates were made at the beginning of the year. Manufacturing overhead Direct labor Department Fabricating Machining Assembly Total Plant $ 353,500 $ 404,000 $90,900 $ 848,400 $ 202,000 $101,000 $303,000 $ 606,000 Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturing costs in the three departments as follows: Direct materials Fabricating $3,200 Department Machining $ 200 Direct labor $3,200 $ 500 Manufacturing overhead 2 Assembly $1,600 $6,400 7 Total Plant $5,000 $10,100 Required: 1. Using the company's plantwide approach: a. Compute the plantwide predetermined rate for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 2. Suppose that instead of using a plantwide predetermir overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions: a. Compute the predetermined overhead rate for each department for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 4. Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead). a. What was the company's bid price on the Koopers job using a plantwide predetermined overhead rate? b. What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost? Complete this question by entering your answers in the tabs below. Req 1A Req 18 Req 2A Req 28 Req 4A Req 48 Using the company's plantwide approach, compute the plantwide predetermined rate for the current year. Predetermined overhead rate % of direct labor cost Complete this question by entering your answers in the tabs below. Req 1A Req 18 Req 2A Req 28 Req 4A Req 48 Using the company's plantwide approach, determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. Manufacturing overhead cost applied Complete this question by entering your answers in the tabs below. Req 1A Req 18 Req 2A Req 28 Req 4A Req 48 Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Compute the predetermined overhead rate for each department for the current year. Predetermined Overhead Rate Fabricating department % of direct labor cost Machining department % of direct labor cost Assembly department % of direct labor cost Complete this question by entering your answers in the tabs below. Req 1A Req 18 Req 2A Req 28 Req 4A Req 48 Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. Manufacturing overhead cost applied Complete this question by entering your answers in the tabs below. Req 1A Req 1B Req 2A Req 28 Req 4A Req 48 Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead). What was the company's bid price on the Koopers job using a plantwide predetermined overhead rate? Company's bid price Complete this question by entering your answers in the tabs below. Req 1A Req 18 Req 2A Req 28 Req 4A Req 48 Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead). What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost? Manufacturing overhead cost applied

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advanced Accounting

Authors: Floyd A. Beams, Joseph H. Anthony, Bruce Bettinghaus, Kenneth Smith

13th edition

134472144, 978-0134472140

More Books

Students also viewed these Accounting questions

Question

Briefly discuss how uncertainty affects capacity decisions.

Answered: 1 week ago