Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Blast it! said David Wilson, president of Teledex Company. Weve just lost the bid on the Koopers job by $2,000. It seems were either too

Blast it! said David Wilson, president of Teledex Company. Weve just lost the bid on the Koopers job by $2,000. It seems were either too high to get the job or too low to make any money on half the jobs we bid.

Teledex Company manufactures products to customers specifications and operates a job-order costing system. Manufacturing overhead cost is applied to jobs on the basis of direct labor cost. The following estimates were made at the beginning of the year:

Department

_______________________________________________________________________

Fabricating Machining Assembly Total Plant

Direct labor $200,000 $100,000 $300,000 $600,000

Manufacturing overhead $350,000 $400,000 $ 90,000 $840,000

Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturing costs in the three departments as follows:

Department

______________________________________________________________________

Fabricating Machining Assembly Total Plant

Direct materials $3,000 $200 $1,400 $4,600

Direct labor $2,800 $500 $6,200 $9,500

Manufacturing overhead ? ? ? ?

The company uses a plantwide overhead rate to apply manufacturing overhead cost to jobs.

REQUIRED:

1. Assuming use of a plantwide overhead rate:

a. Compute the rate for the current year.

b. Determine the amount of manufacturing overhead cost that would have been applied to the

Koopers job.

2. Suppose that instead of using a plantwide overhead rate, the company had used a separate

predetermined overhead rate in each department. Under these conditions:

a. Compute the rate for each department for the current year.

b. Determine the amount of manufacturing overhead cost that would have been applied to the

Koopers job.

3. Explain the difference between the manufacturing overhead that would have been applied to

the Koopers job using the plantwide rate in question 1 (b) above and using the departmental

rates in question 2 (b).

4. Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost

(direct materials, direct labor, and applied overhead). What was the companys bid price on

the Koopers job? What would the bid price have been if departmental overhead rates had been

used to apply overhead cost?

5. At the end of the year, the company assembled the followingactualcost data relating to all

jobs worked on during the year.

Department

_______________________________________________________________________

Fabricating Machining Assembly Total Plant

Direct materials $190,000 $ 16,000 $114,000 $320,000

Direct labor $210,000 $108,000 $262,000 $580,000

Manufacturing overhead $360,000 $420,000 $ 84,000 $864,000

Compute the under- or overapplied overhead for the year (a) assuming that a plantwide

overhead rate is used, and (b) assuming that departmental overhead rates are used.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting Information For Business Decisions

Authors: Loren A Nikolai, Billie Cunningham, John D Bazley

3rd Edition

1111066884, 9781111066888

More Books

Students also viewed these Accounting questions

Question

13. Give four examples of psychological Maginot lines.

Answered: 1 week ago