Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Blast it! said David Wilson, president of Teledex Company. We've just lost the bid on the Koopers job by $4,000. It seems we're either too

image text in transcribed

"Blast it!" said David Wilson, president of Teledex Company. We've just lost the bid on the Koopers job by $4,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to jobs. The following estimates were made at the beginning of the year: Manufacturing overhead Direct labor Fabricating $ 357,000 $ 204,000 Department Machining $ 408,000 $ 102,000 Assembly $ 91,800 $ 306,000 Total Plant $ 856,800 $ 612,000 Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturing costs in the three departments as follows: Direct materials Direct labor Manufacturing overhead Department Fabricating Machining $ 3,400 $ 300 $ 3,600 $ 600 ? ? Assembly $ 1,800 $ 6,600 ? Total Plant $ 5,500 $ 10,800 2 Required: 1. Using the company's plantwide approach: a. Compute the plantwide predetermined rate for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 2. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions: a. Compute the predetermined overhead rate for each department for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 4. Assume that it is customary in the industry to bid Jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead). a. What was the company's bid price on the Koopers job using a plantwide predetermined overhead rate? b. What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost? Complete this question by entering your answers in the tabs below. Required 1A Required 1B Required 2A Required 2B Required 4A Required 4B Using the company's plantwide approach, compute the plantwide predetermined rate for the current year. Predetermined overhead rate % of direct labor cost

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting For Payroll

Authors: Steven M. Bragg

1st Edition

0471251089, 9780471251088

More Books

Students also viewed these Accounting questions

Question

What is job enlargement ?

Answered: 1 week ago

Question

what is the most common cause of preterm birth in twin pregnancies?

Answered: 1 week ago

Question

Which diagnostic test is most commonly used to confirm PROM?

Answered: 1 week ago

Question

What is the hallmark clinical feature of a molar pregnancy?

Answered: 1 week ago