Question
Blast it! said David Wilson, president of Teledex Company. Weve just lost the bid on the Koopers job by $3,000. It seems were either too
Blast it! said David Wilson, president of Teledex Company. Weve just lost the bid on the Koopers job by $3,000. It seems were either too high to get the job or too low to make any money on half the jobs we bid. |
Teledex Company manufactures products to customers specifications and operates a job order costing system. Manufacturing overhead cost is applied to jobs on the basis of direct labor cost. The following estimates were made at the beginning of the year: |
Department | ||||||||
Fabricating | Machining | Assembly | Total Plant | |||||
Direct labor | $ | 218,000 | $ | 109,000 | $ | 327,000 | $ | 654,000 |
Manufacturing overhead | $ | 381,500 | $ | 436,000 | $ | 98,100 | $ | 915,600 |
Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturing costs in the three departments as follows: |
Department | ||||||||
Fabricating | Machining | Assembly | Total Plant | |||||
Direct materials | $ | 4,800 | $ | 500 | $ | 3,200 | $ | 8,500 |
Direct labor | $ | 6,400 | $ | 800 | $ | 8,000 | $ | 15,200 |
Manufacturing overhead | ? | ? | ? | ? | ||||
The company uses a plantwide overhead rate to apply manufacturing overhead cost to jobs. |
Required: | |
1. | Assuming use of a plantwide overhead rate: |
a. | Compute the rate for the current year. |
|
b. | Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. |
|
2. | Suppose that instead of using a plantwide overhead rate, the company had used a separate predetermined overhead rate in each department. Under these conditions: |
a. | Compute the rate for each department for the current year. |
|
b. | Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. |
|
4. | Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead). |
a. | What was the company's bid price on the Koopers job if a plantwide overhead rate had been used to apply overhead cost? |
|
b. | What would the bid price have been if departmental overhead rates had been used to apply overhead cost? |
|
5. | At the end of the year, the company assembled the following actual cost data relating to all jobs worked on during the year. |
Department | ||||||||
Cutting | Machining | Assembly | Total plant | |||||
Direct materials | $ | 208,000 | $ | 17,800 | $ | 132,000 | $ | 357,800 |
Direct labor | 228,000 | 126,000 | 280,000 | 634,000 | ||||
Manufacturing overhead | $ | 393,000 | $ | 478,000 | $ | 86,700 | $ | 957,700 |
a. | Compute the underapplied or overapplied overhead for the year, assuming that a plantwide overhead rate is used. |
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started