Question
Blast it! said David Wilson, president of Teledex Company. Weve just lost the bid on the Koopers job by $4,000. It seems were either too
Blast it! said David Wilson, president of Teledex Company. Weve just lost the bid on the Koopers job by $4,000. It seems were either too high to get the job or too low to make any money on half the jobs we bid. |
Teledex Company manufactures products to customers specifications and operates a job order costing system. Manufacturing overhead cost is applied to jobs on the basis of direct labor cost. The following estimates were made at the beginning of the year: |
Department | ||||||||
Fabricating | Machining | Assembly | Total Plant | |||||
Direct labor | $ | 204,000 | $ | 102,000 | $ | 306,000 | $ | 612,000 |
Manufacturing overhead | $ | 357,000 | $ | 408,000 | $ | 91,800 | $ | 856,800 |
Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturing costs in the three departments as follows: |
Department | ||||||||
Fabricating | Machining | Assembly | Total Plant | |||||
Direct materials | $ | 3,400 | $ | 300 | $ | 1,800 | $ | 5,500 |
Direct labor | $ | 3,600 | $ | 600 | $ | 6,600 | $ | 10,800 |
Manufacturing overhead | ? | ? | ? | ? | ||||
The company uses a plantwide overhead rate to apply manufacturing overhead cost to jobs. |
Required: | |
1. | Assuming use of a plantwide overhead rate: |
a. | Compute the rate for the current year. |
b. | Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. |
2. | Suppose that instead of using a plantwide overhead rate, the company had used a separate predetermined overhead rate in each department. Under these conditions: |
a. | Compute the rate for each department for the current year. |
b. | Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. |
4. | Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead). |
a. | What was the company's bid price on the Koopers job if a plantwide overhead rate had been used to apply overhead cost? |
b. | What would the bid price have been if departmental overhead rates had been used to apply overhead cost? |
5. | At the end of the year, the company assembled the following actual cost data relating to all jobs worked on during the year. |
Department | ||||||||
Fabricating | Machining | Assembly | Total plant | |||||
Direct materials | $ | 194,000 | $ | 16,400 | $ | 118,000 | $ | 328,400 |
Direct labor | 214,000 | 112,000 | 266,000 | 592,000 | ||||
Manufacturing overhead | $ | 365,000 | $ | 426,000 | $ | 85,300 | $ | 876,300 |
a. | Compute the underapplied or overapplied overhead for the year, assuming that a plantwide overhead rate is used. |
b. | Compute the underapplied or overapplied overhead for the year, assuming that departmental overhead rates are used. (Enter overapplied overhead costs as negative amounts and underapplied overhead costs as positive amounts.) |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started