'Blast itt" said David Wilson, president of Teledex Company. We've just lost the bid on the Koopers job by $3,000, It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to opply its manufacturing overhead (assumed to be all fixed) to jobs. The following estimates were made at the beginning of the year: Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturing costs in the three departments as follows: Required: 1. Using the company's plantwide aporoach a. Compute the plantwide predetermined rate for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 2. Suppose that insead of uyng a plantwide predetermined ovemead rate, the company had used departmental predetermined overtiead rates based on direct labor cost. Under these conditions a. Compute the predetermined overbead rate for each department for the current year. b. Determine the amount of manutacturing overhead cost that would have been applied to the Koopers job 4. Assume that it is custamary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct iaboc, and applied overhead) a. What was the company's bid price on the Koopers job using a plantwide predetermined overhead rate? b. What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost? Complete this question by entering your answers in the tabs below. Using the company's plantwide approach, compute the plantwide predetermined rate for the current year. Complete this question by entering your answers in the tabs below. Using the company's plantwide approach, determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. Complete this question by entering your answers in the tabs below. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Compute the predetermined overhead rate for each department for the current year. Complete this question by entering your answers in the tabs below. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermin overhead rates based on direct labor cost. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. Complete this question by entering your answers in the tabs below. Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead). What was the company's bid price on the Koopers job using a plantwide predetermined overhead rate? Complete this question by entering your answers in the tabs below. Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead). What would the bid price have been if departmental predetermined overhead rates had been used to apply overheod cost