Question
Blossom Construction Company had a contract starting April 2018, to construct a $23800000 building that is expected to be completed in September 2020, at an
Blossom Construction Company had a contract starting April 2018, to construct a $23800000 building that is expected to be completed in September 2020, at an estimated cost of $21800000. At the end of 2018, the costs to date were $9592000 and the estimated total costs to complete had not changed. The progress billings during 2018 were $460000 and the cash collected during 2018 was 3180000. Blossom uses the percentage-of-completion method.
At December 31, 2018 Blossom would report Construction in Process in the amount of:
$9132000.
$880000.
$10472000.
$9592000.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started