Question

1 Approved Answer

Blueprint Problem: Direct labor variance Labor Variance Analysis Labor variance analysis is used primarily as a performance evaluation measure for responsible managers in a segment

Blueprint Problem: Direct labor variance

Labor Variance Analysis Labor variance analysis is used primarily as a performance evaluation measure for responsible managers in a segment of a business. Labor variance occurs when the cost of labor or the amount of labor used deviates from what was budgeted by company management during initial planning, for either a given period of time or for a specific amount of production. Direct labor variance analysis is conducted by comparing the standard direct labor rate for production with the actual direct labor rate incurred for the production of the product.

There are two parts to direct labor variance analysis. The first is a comparison of the standard rate per unit of labor with the actual rate per unit of labor, which results in the determination of the labor rate variance. The second is a comparison of the standard quantity of use of units of labor with the actual quantity of use of units of labor for the actual production achieved, which results in the determination of the labor efficiency (usage) variance.

Labor Rate Variance

This type of variance is concerned with the difference between what was paid for labor and what should have been paid for labor for the actual production achieved.

Which of the following activities are possible causes of labor rate variance? Select "Yes" for all that apply.

image text in transcribed

Gauging the Favorableness of Variances When variances occur, they are described as being either favorable or unfavorable. When actual activity consumes more time or money than initially planned, an unfavorable variance exists. However, when actual activity consumes less time or money than initially planned, a favorable variance exists. Note that the terms favorable and unfavorable are used, rather than saying that a variance is good or bad, because until the cause of a variance is discovered, it is not clear whether a variance is either good or bad.

Note: Use the minus sign to indicate negative values (when the budgeted amount is greater than the actual).

image text in transcribed

Standard Direct Labor Cost The controller at your shoemaking company has determined that under normal conditions, you will pay your employees $8.30 per hour, and it will take 2.6 hours of labor per pair of shoes. Given this information, calculate the standard cost of labor per pair of shoes. If required, round the standard labor per pair of shoes to the nearest cent.

image text in transcribed

Actual Direct Labor Cost During March, your shoe-making company incurred actual direct labor costs of $58,872 for 6,690 hours of direct labor in the production of 2,150 pairs of shoes. Given this information, calculate the actual cost of labor per hour. If required, round the actual cost of labor per hour to the nearest cent.

image text in transcribed

APPLY THE CONCEPTS: Conduct the labor variance analysis

Illustrated Example: Calculating Labor Price and Usage Variance

Complete the following graphic to compute the direct labor rate variance, the direct labor efficiency variance, and the total labor cost variance for the production of shoes (in terms of pairs). When required, enter the rates as dollars and cents. If required, use the minus sign to indicate a negative value.

image text in transcribed

1. A lower-skilled laborer doing a higher-skilled task Yes Yes 7 Yes 2A higher-skilled laborer 2. A higher-skilled laborer doing a lower-skilled task 3 Unexpected overtime 3. Unexpected overtime Labor Efficiency. Variance This type of variance is concerned with the difference between the labor hours that were actually used and the labor hours that should have bee Which of the following activities are possible causes of labor rate variance? Select "Yes" for all that apply. 1. A higher-than-normal defect level resulting in unplanned additional work 2. Frequent machine breakdowns used . A higher-than-normal defect level resultgnunlannedaddnal ork Yes Y Yes 3. Using outdated time estimates in determining the standard rate for direct laborYes x

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions