Question
Boat Company, which is under contract to the U.S. Navy, assembles troop deployment boats. As part of its research program, it completes the assembly of
Boat Company, which is under contract to the U.S. Navy, assembles troop deployment boats. As part of its research program, it completes the assembly of the first of a new model (PT109) of deployment boats. The Navy is impressed with the PT109. It requests that Pacific Boat submit a proposal on the cost of producing another six PT109s. Pacific Boat reports the following cost information for the first PT109 assembled and uses a 90 % cumulative average-time learning model as a basis for forecasting direct manufacturing labor-hours for the next six PT109s. (A 90 % learning curve means b = negative 0.152004 .)
Direct material | $ 197 000 |
Direct manufacturing labor time for first boat | 14 900 |
labor-hours | |
Direct manufacturing labor rate | $42 |
per direct manufacturing labor-hour | |
Variable manufacturing overhead cost | $22 |
per direct manufacturing labor-hour | |
Other manufacturing overhead | 25 |
% | of direct manufacturing labor costs |
Tooling |
$ 277,000
Learning curve for manufacturing labor time per boat | 90 |
% | cumulative average b |
|
Tooling can be reused at no extra cost because all of its cost has been assigned to the first deployment boat. |
|
Using the formula for a
90
%
learning curve, b = ln 0.90/ ln 2 = negative 0.105361 / 0.693147 = negative 0.152004
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started