Bodashka is building a home for Galyna that under the original contract is to be completed by December 31. Galyna found the plans for the

Bodashka is building a home for Galyna that under the original contract is to be completed by December 31. Galyna found the plans for the home in a publication focusing on unique houses and is excited because it will be the only home of its type in the area. Because he underestimated the time needed for special and unique framing required for Galyna's house, Bodashka tells Galyna that he needs to hire additional workers in order to have the home done by that time and that Galyna needs to pay him an extra $10,000. Galyna says that she will pay. Bodashka finishes the home and asks for his $10,000. Galyna refuses to pay. What is the likely result if Bodashka sues?

[HINT: You are to discuss which theory of contracts/consideration is applicable and then who will be successful in this scenario.]

Step by Step Solution

3.33 Rating (153 Votes )

There are 3 Steps involved in it

Step: 1

In this scenario the relevant legal concept to consider is the doctrine of consideration in contract law Consideration refers to something of value ex... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

College Accounting Chapters 1-30

Authors: John Price, M. David Haddock, Michael Farina

14th edition

978-1259284861, 1259284867, 77862392, 978-0077862398

More Books

Students also viewed these Law questions

Question

How has health psychology expanded into traditional health fields?

Answered: 1 week ago

Question

Explain the retail method of inventory estimation.

Answered: 1 week ago