Question

1 Approved Answer

BOE Manufacturing is trying to decide between two different conveyor belt systems. System A costs $212,000, has a four-year life, and requires $68,000 in pretax

BOE Manufacturing is trying to decide between two different conveyor belt systems. System A costs $212,000, has a four-year life, and requires $68,000 in pretax annual operating costs. System B costs $300,000, has a six-year life, and requires $62,000 in pretax annual operating costs. Both systems are to be depreciated straight-line to zero over their lives and will have zero salvage value. Whichever project is chosen, it will not be replaced when it wears out. The tax rate is 30 percent and the discount rate is 9 percent.

Calculate the NPV for both conveyor belt systems. (Negative amounts should be indicated by a minus sign. Round your answers to 2 decimal places (e.g., 32.16).)

NPV
System A $
System B $

Which conveyor belt system should the firm choose?
System A
System B

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Securitisation Derivatives A Practioner's Handbook

Authors: Mark Aarons, Vlad Ender, Andrew Wilkinson

1st Edition

1119532272, 978-1119532279

More Books

Students also viewed these Finance questions

Question

6. How do histories influence the process of identity formation?

Answered: 1 week ago