Bonus Project Gemini is an atypical project. You have overestimated the efficiency of your project team to complete the project work. Your actual project costs
Bonus Project Gemini is an atypical project. You have overestimated the efficiency of your project team to complete the project work. Your actual project costs are $45,000, the BA is $250,000, the earned value (EV) is $37,500. What is the ETC