Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Bonus question (30 points): Your company is experiencing severe financial difficulties, but the project is still needed. As the project manager, you need to complete

Bonus question (30 points):

Your company is experiencing severe financial difficulties, but the project is still needed. As the project manager, you need to complete the project with minimum cost. The project duration can be extended as needed.

  1. What would be the lowest cost of the project (Without worrying about the time)? (15 points)

Answer: The lowest cost of the project would be $0. This can be achieved by not assigning any resources to the project activities. Since the project duration can be extended as needed, there is no need to worry about the time.

b) With the lowest cost, what would be the shortest project duration? Describe your method/operation and explain why. (you can re-assign resources if the roles are the same, but no one should be overloaded). (15 points)

The description of the solution needs to be thorough, and all necessary supporting screenshots need to be provided, or no credit will be received.

What you cannot change:

the budgeted labor hours and proper roles (position/specialty) of each activity

the salary of each employee (resource)

Activity dependencies

the existing resources of this project (not every one of them has to be utilized)

What you can change:

resource assignment (if the roles are appropriate)

Note 1: The total Planned Labor Units is 304 hours. Please make sure that at the end of this assignment, the total Planned Labor Units and the Planned Labor Units for each activity are not changed.

Note 2: When re-allocating resources to an activity, the job titles (Roles) designated for each activity should not be changed. e.g. for activity "Class diagram", both System Analyst and System Architect are needed. So, you will need to assign at least one System Analyst and one System Architect to the activity, or assign the resource (employee) that has both roles.

image text in transcribed
Layout: Classic Schedule Layout Filter: All Activities Activity ID Activity Name Planned Labor Units - AA2-2 Automated Advising 5 304h AA2-2.1 Communication and Administration Team Oh AA2-2.1.1 Stakeholder communication Oh AA2-2.1.2 Engineer communication Oh AA2-2.2 System architect Team 192h AA2-2.2.1 Current system analysis Oh AA2-2.2.2 New system design 192h A1200 Improved use-case diagram 8h O A1210 Process diagram level one 16h A1220 Process diagram level two 24h A1250 Entity-relationship-diagram for 40h A1260 Class diagram 24h A1270 Developing data consolidatic 24h A1280 Web theme design 24h A1290 Student page design 8h A1300 Faculty/staff page design 8h O A1320 Improving design 16h AA2-2.3 Programmer Team 112h A1330 Webpage coding 40h A1340 Function algorithm developm 56h A1350 Webpage function programm 16h

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Leading And Collaborating In A Competitive World

Authors: Thomas S Bateman, Scott A Snell, Robert Konopaske

15th International Edition

978-1265051303

More Books

Students also viewed these General Management questions

Question

If the job involves a client load or caseload, what is it?

Answered: 1 week ago

Question

=+Could you use an ambient ad?

Answered: 1 week ago