BONUS: Your project manager asked you to determine the labor cost per unit based upon the productivity and average cost of one of your crews.
BONUS: Your project manager asked you to determine the labor cost per unit based upon the productivity and average cost of one of your crews. What is the labor cost per unit for the following crew? (Round to nearest cent)
- Weighted Average Labor Cost = $44.00 per labor hour
- Productivity Rate (Labor Hours/Unit) = 0.200