Boris is a project manager and has been assigned a small project to correct a bug in a mobile app. He needs a quick and
Boris is a project manager and has been assigned a small project to correct a bug in a mobile app. He needs a "quick and dirty" estimate for activity durations, so he uses this technique: (For Ref Only,Question #: PM-02302) Group of answer choices Bottom-up estimating Analogous estimating Historical information from previous projects Parametric estimating