Both Projects A and B are acceptable as independent projects. However, the selection of either one of these projects eliminates the option of selecting the
Both Projects A and B are acceptable as independent projects. However, the selection of either one of these projects eliminates the option of selecting the other project. Which one of the following terms best describes the relationship between Project A and Project B?
Mutually exclusive
Conventional
Multiple choice
Dual return
Crosswise