Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began in 2018 and was completed in 2020. The following

Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars.

Estimated Costs to Complete

Costs Incurred During Year

(As of the End of the Year)

Situation

2018

2019

2020

2018

2019

2020

1 1,630 2,520 1,290 3,810 1,290
2 1,630 1,290 2,920 3,810 2,920
3 1,630 2,520 2,640 3,810 2,540
4 630 3,130 1,260 4,410 940
5 630 3,130 2,210 4,410 2,540
6 630 3,130 3,100 5,855 2,870

Required: Complete the following table. (Do not round intermediate calculations. Enter answers in dollars. Round your final answers to the nearest whole dollar. Negative amounts should be indicated by a minus sign.)image text in transcribed

Gross Profit (Loss) Recognized Revenue Recognized Over Time Revenue Recognized Upon Completion Situation 2018 2019 2020 2018 2019 2020 2 4

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting An Introduction

Authors: Alex Watson, Jacqui Kew

5th Edition

0190425520, 978-0190425524

More Books

Students also viewed these Accounting questions