Question

1 Approved Answer

Brandon Inc. uses ABC to account for its chrome wheel manufacturing process campaign managers have identified for manufacturing activities anchor manufacturing overhead costs materials handling

Brandon Inc. uses ABC to account for its chrome wheel manufacturing process campaign managers have identified for manufacturing activities anchor manufacturing overhead costs materials handling machine set up insertion of parts and finishing the budgeted activity cost for the upcoming year and they're allocation faces are as follows
job 420 used 275 parts, required 2 set ups a d consumed 120 finishing hours
job 510 used 650 parts, required 6 set ups a d consumed 390 finishing hours
image text in transcribed
image text in transcribed
image text in transcribed
Bradenton Inc. expects to produce 1.000 chrome wheels during the year. The wheels are expected to use 3.200 parts, require 25 set-ups, and consume Job 420 used 275 ports, required 2 set-ups, and consumed 120 Finishing hours Job 510 used 650 parts, required 6 set-ups, and consumed 390 finishing hours Roonents Requirement 1. Compute the cost allocation rate for each activity Fint identify the formula, and then compute the rate for each activity Mat handling Machine setup Activity overhead rato part setup Insertion part hour Finishing Requirement 2. Compute the manufacturing overhead cost that should be assigned to Job 420, Activity MOH Cost Material handling Machine setup Insertion of parts Finishing Total Requirement 3. Compute the manufacturing overhead cost that should be assigned to Job 510 Activity MOH Cost Materials handling Machine setup Insertion of parts Finishing Total part setup part 1 hour Requirements 1. Compute the cost allocation rate for each activity. 2. Compute the MOH cost that should be assigned to Job 420. 3. Compute the MOH cost that should be assigned to Job 510. Print Done estion pected to use 3.200 parts, require 25 set-ups, and consume 2,300 hours of finishing time. Active overhead Budgeted costs and activity bases - X 420 Activity Material handling Machine set-up Insertion of parts Finishing Total Budgeted Manufacturing Overhead Cost $ 8.400 9,000 54,400 89,700 $ 159,500 Allocation Base Number of parts Number of set-ups Number of parts Finishing direct labour hours Reqy Total 1. Co 2. Co 3. Co 510 Print Done no question NacBook Air

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Value Based Management Context And Application

Authors: Glen Arnold, Matt Davies

1st Edition

0471899860, 978-0471899860

More Books

Students also viewed these Accounting questions

Question

(1), 4761.

Answered: 1 week ago