Break - even cash inflows and risk Boardman Gases and Chemicals is a supplier of highly purified gases to semiconductor manufacturers. A large chip producer
Breakeven cash inflows and risk Boardman Gases and Chemicals is a supplier of highly purified gases to
semiconductor manufacturers. A large chip producer has asked Boardman to build a new gas production facility close
to an existing semiconductor plant. Once the new gas plant is in place, Boardman will be the exclusive supplier for
that semiconductor fabrication plant for the subsequent years. Boardman is considering one of two plant designs.
The first is Boardman's "standard" plant which will cost $ million to build. The second is for a "custom" plant
which will cost $ million to build. The custom plant will allow Boardman to produce the highly specialized gases
required for an emergency semiconductor manufacturing process. Boardman estimates that its client will order $
million of product per year if the standard plant is constructed, but if the custom design is put in place, Boardman
expects to sell $ million worth of product annually to its client. Boardman has enough money to build either type
of plant, and, in the absence of risk differences, accepts the project with the highest NPV The cost of capital is
a Find the NPV for each project. Are the projects acceptable?
b Find the breakeven cash inflow for each project.
c The firm has estimated the probabilities of achieving various ranges of cash inflows for the two projects, as shown
in the table What is the probability that each project will achieve the breakeven cash inflow found in part b
d Which project is more risky? Which project has the potentially higher NPV Discuss the riskreturn tradeoffs of the
two projects.
e If the firm wished to minimize losses that is NPV $ which project would you recommend? Which would you
recommend if the goal was achieving a higher NPV
a The NPV for project "standard" is $ Round to the nearest cent.Question
a The NPV for project "standard" is $
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started