Brief Case Study -- IT project budgets fall off the rails Dubbed Making It Work For You, the $425 million project was meant to transform
Brief Case Study -- IT project budgets fall off the rails Dubbed “Making It Work For You”, the $425 million project was meant to transform the information technology systems for the state's transport agencies. But internal documents released under freedom of information laws show the major IT project for Transport for NSW has completed only a third of its end-user goals despite spending $348 million since it began almost five years ago.
A report from a consulting firm hired by Transport for NSW found last month (February 2018) that the IT service delivery team established in 2011 is facing substantial challenges including a lack of funds to deliver the capabilities to successfully function as a systems integrator.
And with the “Making It Work For You” project now scheduled to put in place “significant technical change”, the report dated February 19 this year (2018) warned of “large end-user impacts in the next four months”
Questions: Using this brief case study, identify and explain the problems happened in the view of IT project management.
I expect 5 problems to be identified and discussed. Problems could include— budget, scope, project evaluation process, end user requirements, possible specific challenges faced by the project team.
Words breakdown:
- Budget (Word count 300)
- Scope (Word count 300)
- Project evaluation process (Word count 300)
- End user requirements (Word count 300)
- Possible specific challenges (Word count 300)
For your understanding I have provided the case below:
Transport For NSW
Case Study -- IT project budgets fall off the rails
Dubbed “Making It Work For You”, the $425 million project was meant to transform the information technology systems for the state's transport agencies.
But internal documents released under freedom of information laws show the major IT project for Transport for NSW has completed only a third of its end-user goals despite spending $348 million since it began almost five years ago.
A report from a consulting firm hired by Transport for NSW found last month (February 2018) that the IT service delivery team established in 2011 is facing substantial challenges including a lack of funds to deliver the capabilities to successfully function as a systems integrator.
A final report by Third Horizon marked “confidential” and “sensitive”, paints a worrying picture of the state of IT systems at Transport for NSW and the agencies which fall under its control such as Sydney Trains, bus operator State Transit and Roads and Maritime Services.
Financial benefits from centralizing IT functions “are not being fully realized”, the service delivery performance appeared to be “worsening” and its credibility was declining. In a broad swipe, the report said the IT service delivery “does not appear to be meeting the service requirements” of the transport agencies, resulting in “significant broader impacts”.
Apart from factors such as “technical complexity”, it raised concerns about “governance issues” and took a shot at the “mindsets and behaviours” of those in the IT team that “hinder improvement”, warning that “major interventions” were needed to fix the situation.
And with the “Making It Work For You” project now scheduled to put in place “significant technical change”, the report dated February 19 this year (2018) warned of “large end-user impacts in the next four months”.
Greens transport spokeswoman, Mehreen Faruqi, who obtained the report by using freedom of information laws, said the government needed to reveal whether the IT project would ever be completed and how much more public money would be wasted.
“This government has boasted about going digital but a project that was supposed to deliver the most basic technology upgrade to one of its largest agencies has completely fallen through,” she said. “Ultimately, taxpayers bear the cost of their inability to deliver projects to budget and on time.”
Transport for NSW said in a statement that the IT project remained within the approved funding envelope and was “delivering against” a revised scope put in place in March 2017, which would be completed later this year.
The Third Horizon report does not mention the revised scope last year but has made a series of recommendations, including the need for “stronger leadership” and changes to the IT team's “structure and capacity”.
Step by Step Solution
3.43 Rating (159 Votes )
There are 3 Steps involved in it
Step: 1
Poor budget for the Make It Work for You IT project a 425 million IT transformation project for government transportation agencies But internal documents released under the Freedom of Information Act ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started