Question
Brighton Rock Manufacturing Company[1] The background: Graham Hale, Controller of Brighton Rock Manufacturing Company (BRMC), a local machining shop with several computer controlled machine tools,
Brighton Rock Manufacturing Company[1]
The background:
Graham Hale, Controller of Brighton Rock Manufacturing Company (BRMC), a local machining shop with several computer controlled machine tools, was contemplating the pricing for a new order that had just arrived. The customer requested that BRMC submit a bid for the fabrication of 100 units of a complex product that the company had never built before (although it is well within their capabilities and compatible with current products). BRMCs engineers would have to spend time developing the process routines to machine the components required for the product. Hale wondered whether the usual markup of 35% over manufacturing cost would really be adequate for this order.
BRMCs current product costing system:
Materials for the order would cost $12.40 per unit of finished product. The product would require 0.6 direct labor hours and 0.8 machine hours per unit manufactured. The companys direct labor rate is $20 per direct labor hour. Overhead is currently applied to products using two rates: 200% of direct labor dollars (cost), and $70 per machine hour.
Thus the cost per unit of this order would be calculated as follows:
Direct materials $ 12.40
Direct labor 0.6 * $20 12.00
DL based overhead 200% * $12.00 24.00
MH based overhead 0.8 * $70 56.00
Total cost per unit produced $104.40
The total cost of the order would therefore be 100 * $104.40, or $10,440. Adding the 35% markup, BRMC would bid $10,440 * 1.35, or $14,094 for the job. Hales concern is concerned that this bid would not pay for all the engineering effort, and also the selling and administrative expenses, and still leave any actual profit.
What about a different costing system: ABC?
Hale recalls that several months ago a summer intern from performed a simple activity-based study of BRMCs operations as part of a work-study project. Hale searched his files and found the report the student had prepared. He saw that the student had developed the following list of activities, cost drivers, and activity rates.
ACTIVITY | COST DRIVER | ACTIVITY RATE |
Process customer orders | Number of customer orders | $100 / order |
Provide engineering design and support | Engineering hours | $75 / engineering hour |
Purchase and receive components | Number of purchase orders | $150 / purchase order |
Schedule production and perform first-item inspections | Number of production runs | $200 / production run |
Set up machines | Number of set up hours | $80 / set up hour |
Machine processing | Machine hours | $60 / machine hour |
Direct labor assembly | Direct labor hours | $50 / DLH |
Hale went on to estimate the quantity of each activity cost driver this new order would require.
Activity cost driver | Quantity for 100 units |
Number of purchase orders | 10 |
Number of production runs* | 6 |
Setup time per production run | 3 hours |
Number of customer orders | 1 |
Engineering design and process time | 20 hours |
* A separate production run would be required to custom machine some of the components before assembly into the final product.
REQUIRED:
Hale speaks of administrative expenses that the bid (using traditional costing) might not be able to cover. What might some of these expenses be? Is their quantity likely to be affected by this order? Explain.
We listed the steps in developing an ABC system as being:
Define activities.
Identify the cost of each activity.
Define a cost driver for each activity.
Calculate an activity (overhead) rate for each activity.
Use the activity rates to assign activity costs to the product.
The table does not show the total cost of each activity. Be certain you understand where the result of steps (a), (c) and (d) are reflected in the table.
Identify each activity in the table as Unit, Batch, or Product level.
Calculate the total cost of the order using activity based overhead application. Dont forget the materials and labor costs. What would the bid to the customer be if BRMC continues to use the 35% mark up?
Explain why the number you obtain is so different from the one Hale obtained using the companys current overhead application rates. Is it better, or just different? Give at least two factors that suggest the company should use activity based costing for its specialty products.
| BRIGHTON ROCK MANUFACTURING CO. | Notes on Brighton Rock: | ||||||||||||||||
Total cost per unit produced: | 100 | units ordered | 1. Remember there are TWO costs of direct labor workers to the company: | |||||||||||||||
Direct materials | $12.40 | a. DIRECT LABOR: what they PAY the people. | ||||||||||||||||
Direct labor 0.6 * $20 | 12.00 | $20 | per DLH | 0.6 | DLH/unit | b. Direct labor OVERHEAD SUPPORT - this is the ACTIVITY that is ALLOCATED based | ||||||||||||
DL based OH 200% * $12 | 24.00 | 200% | of DL$ | on direct labor. | ||||||||||||||
MH based OH 0.8 * $70 | 56.00 | $70 | per MH | 0.8 | MH/unit | 2. A BATCH level activity is done ONCE for as many UNITS as you need to process. | ||||||||||||
Total cost | $104.40 | It doesn't depend on units, but rather on how many times you do that ACTIVITY. | ||||||||||||||||
3. In Question 2, I am asking for a VERY SHORT explanation of how BRMC estimated total cost | ||||||||||||||||||
Markup | 35% | of mfg cost | and total units of activity, and calculated the activity rate. | |||||||||||||||
Total order cost for 100 units | $10,440.00 | total cost to produce using TRADITIONAL costing | This is a question of UNDERSTANDING. You are given an activity RATE, but not | |||||||||||||||
Total bid @ mfg cost * 1.35 | $14,094.00 | total bid to customer with 35% markup | where (what numbers) the rate came from. Just do ONE rate, not all of them. | |||||||||||||||
4. For Question 1: you are calculating what it will cost BRMC to make this order. Why does | ||||||||||||||||||
ACTIVITY | COST DRIVER | ACTIVITY RATE | it matter? What other "numbers" (revenues, costs) in the company will that | |||||||||||||||
Process customer orders | # of orders | $100 | per order | affect? What WON'T it affect? | ||||||||||||||
Provide engineering design / support | Engineering hr | $75 | per eng hr | |||||||||||||||
Purchase / receive components | # of PO's | $150 | per PO | |||||||||||||||
Schedule production / 1st inspection | # of prod runs | $200 | per prod run | |||||||||||||||
Set up machines | # of setup hrs | $80 | per SU hr | |||||||||||||||
Machine process | machine hr | $60 | per MH | |||||||||||||||
DL assembly | DLH | $50 | per DLH | |||||||||||||||
Cost drivers required by the order: | ||||||||||||||||||
# of PO's | 10 | |||||||||||||||||
# of production runs | 6 | |||||||||||||||||
SU hr per production run | 3 | |||||||||||||||||
# of customer orders | 1 | |||||||||||||||||
Engineering hr | 20 | |||||||||||||||||
Activity levels: | ||||||||||||||||||
3. Process customer orders | ||||||||||||||||||
Provide engineering design / support | ||||||||||||||||||
Purchase / receive components | ||||||||||||||||||
Schedule production / 1st inspection | ||||||||||||||||||
Set up machines | ||||||||||||||||||
Machine process | ||||||||||||||||||
DL assembly | ||||||||||||||||||
4. Cost of the order (total): | ||||||||||||||||||
Direct labor | given | |||||||||||||||||
Direct materials | given | |||||||||||||||||
Overhead: process orders | ||||||||||||||||||
Engineering design/support | ||||||||||||||||||
Purchase/receive components | ||||||||||||||||||
Schedule production | ||||||||||||||||||
Set up machines | ||||||||||||||||||
Machine process | ||||||||||||||||||
DL assembly | ||||||||||||||||||
Total cost of the order | ||||||||||||||||||
Cost per unit ( 100) | ||||||||||||||||||
Add markup of 35% = bid to customer | ||||||||||||||||||
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started