Question
Bronson Machining, Inc., manufactures driveway security fences and gates. It wants to develop an input-output control report for its welding work center for 5 weeks
Bronson Machining, Inc., manufactures driveway security fences and gates. It wants to develop an input-output control report for its welding work center for 5 weeks (weeks 6/6 through 7/4). The planned input is 280 standard hours per week. The actual input is close to this figure, varying between 250 and 285. Output is scheduled at 320 standard hours, which is the assumed capacity. A backlog exists in the work center.
APPROACH
Bronson uses schedule information to createFigure15.2, which monitors the workload-capacity relationship at the work center.
SOLUTION
The deviations between scheduled input and actual output are shown inFigure15.2. Actual output (270 hours) is substantially less than planned. Therefore, neither the input plan nor the output plan is being achieved.
INSIGHT
The backlog of work in this work center has actually increased by 5 hours by week 6/27. This increases work-in-process inventory, complicating the scheduling task and indicating the need for manager action.
LEARNING EXERCISE
If actual output for the week of 6/27 was 275 (instead of 270), what changes?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started