BSBPMG534 - Task 2 Study Case You have been recently engaged by XYZ Pty Ltd trading as MMI as a Project Manager (PM) to develop

BSBPMG534 - Task 2

Study Case

You have been recently engaged by XYZ Pty Ltd trading as MMI as a Project Manager (PM) to develop and implement a project to open a new campus in Sydney (refer to MMI strategic objectives).

  • The Board of Directors (BoD) has allocated 3 million dollars to the project.
  • Project duration: 1 year.
  • You can employe four new staff members to be part of the project team for its duration. Source the rest of the project team from existing MMI personnel (flexible work arrangements will be needed)

The project includes:

  • Finding premises in Sydney CBD ( 800-1000 square metres, onsite parking for staff, natural light)

Ideally, there will be enough room for 5-7 classes, one meeting room, one computer lab, 1 x student kitchen, student lounge, 1 x staff kitchen, three offices for staff, toilet facilities

  • Rent the premise
  • Obtain necessary permits
  • Source architect and building company
  • Source and buy furniture and equipment
  • Liaise with the architect and building company

The project steering committee is composed of:

  • Mr Eli Brown - Non-executive Director
  • Mr Leonard Black - CFO
  • Academic Manager (Jacob Graham)

The project sponsor is Taylor Varin (Client Service Manager), played by the trainer and assessor.

You will have to:

  • Determine the project requirements
  • Work in collaboration with pertinent stakeholders
  • Scope the project
  • Cost and resource the project
  • Develop the project plan
  • Execute the project
  • Finalise the project

Task 2.1Plan project human resources

Read the scenario for assessment and consult with the project team, considering input and feedback from the project team when completing this task.

Consult with the project sponsor (played by the trainer and assessor in the simulated work environment) and the project team as needed.

  1. Work Breakdown Structure (WBS)

Develop a Work Breakdown Structure to set out the project organisation and structure. This will help you align individual and group competencies with project tasks.

You can develop the WBS as a chart or as a list; it can be by function or by project phase.

Copy and paste your WBS below:

  1. Project Human Resource Plan

Determine the human resource requirements for the project and com ple te the project human resource plan in Template 1. Follow the instructions provided.

Template 1 -Project Human Resource Plan

Project Human Resources Management Approach

Development

Outline the following:

  • Outline the significant inputs into the HR plan (2-3)
  • Outline what HR legislations, regulations and policy and procedures are taken into consideration and why (3-4)
  • Outline what issues could impact on project HR management (2-3)

ANSWER

Project Team Recruitment and Selection Strategy

Summarise how the project team is recruited and selected (50-80 w or ds)

ANSWER

Project Team Performance Review Strategy

Summarise how the work performance of the project team is monitored and reviewed. (40-80 w o r ds)

ANSWER

Project Team engagement strategy

Summarise how the project team is engaged and how a collaborative, efficient and innovative work environment is created for the team. (40-80 w or ds)

ANSWER

Project Team training strategy

Summarise the development and training opportunities for the team. (40-80 w o r ds)

ANSWER

Project Team Needs Analysis

Analyse and determine the HR needs of the team. (6-8 team members)

Project deliverable / WBS package/Objective

Skills

Knowledge

Attributes

HC (Head Count) Work arrangements

Existing staff

Y/N

Proposed start and finish date

Example:

Web site design

Example:

Experience with web design projects

Certificate IV in IT

Example:

1

Example:

9-5

Mo-Fri

Example:

N

Example:

May2020-Sept 2020

Project Organisational Chart

Develop and include below a project organisational chart.

Project Team Roles and Responsibilities

Com ple te the table provided indicating:

  • Role - description of the portion of the project for which the member is accountable. Add the name of the HR resource attached to the role when applicable.
  • Authority- the level at which the member may make decisions, apply project resources, or approvals. This needs to be detailed: what authority does the role have. For example, the Project Manager may have the authority to sign off employment contracts.
  • Responsibility - the work a team member must perform to com ple te assigned work activities
  • Competency - the skill(s) required to com ple te assigned project activities
  • KPI- 2 KPIs to measure individual's performance
ROLE AUTHORITY RESPONSIBILITY COMPETENCY KPI

Example:

Project Team

Member X - Admin support

Example:

NA

Example:

Data Entry

Prep reports

Basic communication with team

Example:

Certificate IV in business

Previous experience in admin support

Example:

Data Entry errors <2%

All reports prepared and distributed by the agreed deadline

RACI Chart

Develop and copy below a RACI Chart for the project either by a task or by WBS package for min. 4-5 project stakeholders. Must include team members (as a project management team), project manager and project sponsor.

  1. Communicate project roles and responsibilities

Wri te an email (Template 2) to the project team, the project sponsor and the project steering committee to:

  • Communicate the inclusions of the project human resource plan (attach the plan to the email)
  • Provide a detailed description of the individual project team members roles and responsibilities, including the project manager

Theemail text should be in grammatically correct English, written in an appropriate (polite, business-like) style.

(150-200 w o r ds)

Template 2 -Email

Email to project team, project sponsor and project steering committee
To:
Cc:
Bcc:
Subject:
Date email is sent:
Attachments:

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Supervision In The Hospitality Industry Leading Human Resources

Authors: John R Walker, Jack E Miller, Walker

6th Edition

0470077832, 9780470077832

More Books

Students also viewed these General Management questions

Question

Self-confidence

Answered: 1 week ago

Question

The number of people commenting on the statement

Answered: 1 week ago