Question
BSG Ensuring Success through effective Stakeholder Management Engagement overview Banking organisations are required to comply with various regulations and governance requirements, depending on their scope
BSG Ensuring Success through effective Stakeholder Management Engagement overview Banking organisations are required to comply with various regulations and governance requirements, depending on their scope of operations. As a global banking group, the bank was required to deal with such regulations at international, national and group level. To achieve consistent levels of compliance across the Group, the bank published a Group Policy on Sanctions and Prohibition of Business Activities. BSG was contracted to achieve compliance with the policy within the bank's emerging market operations. Using the MSP (Managing Successful Programmes) methodology, BSG set out to plan and guide the programme. At the outset of the programme, BSG performed initial analysis and identified three key programme risks: 1. The responsibilities between the UK teams, the local programme team (of which BSG was part) and the in-country stakeholders were poorly defined 2. The flow of information between stakeholder groups (UK, SA and in-country stakeholders) was unclear and inconsistent information was being disseminated, which resulted in confusion and misunderstanding 3. The lack of understanding of the African banking context by the UK Group stakeholders related to daily operational realities within African countries Solution BSG identified stakeholder management as the key mitigating factor for these risks and as such defined a comprehensive stakeholder management plan, which was subsequently followed and actioned in parallel with the business analysis activities: BSG crafted a detailed change management plan, based on the stakeholder analysis, designed to ensure communications from the local programme team to the UK and to the in-country stakeholders was delivered regularly, accurately and in a consistent fashion The team planned and conducted visits to each of the countries within emerging markets to meet with key in-country stakeholders and establish a basis for meeting the programme's requirements. The visits were primarily used to complete detailed process mapping and other business analysis work in each country, but the face-to-face interactions with stakeholders were identified as pivotal relationship building activities The personal interaction with key in-country stakeholders allowed the programme team to establish relationships with the people who were ultimately affected by the changes introduced. The intimate knowledge these stakeholders had of the business, its constraints and challenges and the operating environment was crucial - not only in designing an effective solution, but in obtaining commitment and buy-in to the change from the business users. Effective relationships in the business areas allowed BSG to gather specific information regarding systems, processes, constraints and challenges in each country and ensured a team of committed individuals in each country who were prepared to 'champion' the cause of the programme with reluctant users and stakeholders. This played a major role in translating the high-level requirements into effective business activities. The programme team faced a number of geographic and logistical challenges: 1. Programme stakeholders were spread across 14 countries, three continents and six time zones, which resulted in numerous difficulties, including working time (local time vs. UK time), cultural differences (in the UAE and Egypt, a workweek runs from Sunday to Thursday) and difficulty setting up meetings and visits 2. During the course of the programme, the bank restructured its Africa and Indian Ocean business unit, incorporating it into the Emerging Markets business cluster, which resulted in the regional office being moved from Johannesburg to Dubai. This meant changes to programme stakeholders and reporting lines as well as an extension in scope to include Egypt, India and the UAE 3. The UK office lacked the necessary of understanding of the complexities of the practical realities of operations in Africa and expected branches in the emerging markets to have the same infrastructure and resources as a branch in the UK 4. The sector growth across most of the emerging market countries means they are largely under-resourced, with staff operating consistently at full or near-full capacity. This means they have very little time to devote to project activities, as Business As Usual (BAU) activities must be their priority Through the creation of a sound communication plan, which defined stakeholders in terms of their responsibilities and expectations, taking into account communication requirements and constraints, the programme team was able to effectively management the expectations of key stakeholders. By dealing with each stakeholder level individually, and at country-level, the communications plan, through regular and consistent communications, ensured expectations, risks and delivery were all successfully managed. Expansion of the stakeholder map and communications plan mitigated the impact of the restructuring of the Africa and Indian Ocean business unit. The programme team conducted visits to each country identified in the scope of the project, which enabled the team to proactively identify the disparities between operations in each country and those of the UK. This allowed the team to manage the expectations of the UK Group Programme team and helped maintain feasible milestone schedules and communication of realistic requirements to in-country teams. BSG managed the BAU requirements by grouping together communications and requirements. Testing and training activities were grouped according to release dates, which helped shape the training and change release plans, minimising disruption to BAU. As the staff, in-country did not have the free time available to sit in long training sessions or workshops, BSG designed the training and accompanying communications so it could be effectively distributed within the various countries. Making a Difference BSG believes that stakeholder management alone will not define whether a programme will be a success or a failure, but that effective stakeholder management enhances the success of a programme by reducing the amount of resistance to the future change. Without stakeholder management, the Sanctions Programme would not have failed in terms of delivering capability in the form of compliant systems and processes, but would have been a complete disaster in terms of the effective use of these. Thus, the programme would not have met the overall objectives of achieving compliance without adversely affecting normal business processes. Awareness, buy-in to the change and ownership of the solution by business were all achieved through effective stakeholder management and were critical to succeeding in implementing a compliant and sustainable solution that supported the business
1.1 When creating a communications plan, many considerations must be kept in mind. Critically discuss the project communications plan considerations. Use the table and populate the communication plan considerations that BSG took and then explain the table concisely.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started