Buchanan Corp. forecasts the following payoffs from a project: Outcome Probability of Outcome Assumptions $700 25% pessimistic $3,200 50% moderately successful $5,200 25% optimistic What
Buchanan Corp. forecasts the following payoffs from a project:
Outcome | Probability of Outcome | Assumptions |
$700 | 25% | pessimistic |
$3,200 | 50% | moderately successful |
$5,200 | 25% | optimistic |
What is the expected value of the outcomes?
$3,325
$3,075
$3,033
$3,200