Budget has been really tricky to navigate on the new product build. Once the project has started, yourself as the project manager have done a

Budget has been really tricky to navigate on the new product build. Once the project has started, yourself as the project manager have done a calculation and come up with a value earned of 20,000 but the actual cost was 18,000. 
What is the cost variance, and what does this number tell us? (Is the project ahead of schedule behind schedule? Or under or over budget)?


Step by Step Solution

There are 3 Steps involved in it

Step: 1

The cost variance in project management is a measure of the difference between the earned value the ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management The Managerial Process

Authors: Eric W Larson, Clifford F. Gray

8th Edition

1260570436, 978-1260570434

More Books

Students also viewed these Accounting questions

Question

high proportion of women enrolled in universities

Answered: 1 week ago